Stanford D&T Mechanical Room Control Air Compressor System Upgrade
Industry: Hospitals and Healthcare
Type: Equipment
Description
Kaeser Control Air Compressor System Maintenance Upgrade
Scope of Work
- Provide and Install (2) (N) Kaeser “Air Center” SK 15 Rotary Screw Compressors
- 71 CFM @ 100 PSIG Each to Match Existing, 460V, 3 Phase, 60 Hz, 67 dB(A)
- 5 Gallon Air Receiver with Auto Receiver Tank Drain
- Built-In Refrigerated Kaeser Secotec Dryer
- Condensate Drain CAT Kit Air Center SK15
- Compressed Air Filters F22KE
- Condensate Treatment KCF-50 Condensate Treatment System
- Sigma Control 2 – Compressor “LEAD – LAG” Alternation
- Kaeser Factory Startup-Commissioning x 3
- Phase Planning
- Phase 1 - Designated Temporary Air Compressor
- Rig, Set, and Anchor (1) (N) Kaeser SK 15 Rotary Screw Compressor
- Plumbing
- Provide Temporary POC – Complete POC with Flexible Compressed Air Hose Connection
- Electrical
- Safe-Off - LOTO, Disconnect Power Feeding (1) of the Existing Kaeser Compressors
- (E) 30A Breaker Panel GEZ4A-32,34,36
- Complete Power Wiring to Temporary Compressor Location – Terminate Wires
- Startup and Test
- Safe-Off - LOTO, Disconnect Power Feeding (1) of the Existing Kaeser Compressors
- Phase 2 - Demo
- Demo and Removal of Existing Kaeser SK 19 Rotary Screw Compressors
- Electrical Demo – Including Safe-Off – LOTO
- (E) 30A Breaker Panel GEN4-7,9,11
- Cleanup (E) Equipment Pad
- Phase 3 – (N) Control Air Compressor CAC-2
- Install (1) (N) Kaeser SK 15 Rotary Screw Compressor
- Rig, Set, Seismically Anchor
- Complete Plumbing POC + Condensate Drains
- Complete Electrical Power Conduit – Wire – Terminations
- (E) 30A Breaker Panel GEN4-7,9,11
- Startup and Test
- Phase 4 – (N) Control Air Compressor CAC-1
- Remove 2nd (N) Kaeser SK 15 from Temporary Location. Rig, Set, Seismically Anchor in Final Location.
- Electrical Safe-Off – LOTO
- (E) 30A Breaker Panel GEZ4A-32,34,36
- Complete Plumbing POC + Condensate Drains
- Complete Electrical Power Conduit – Wire- Terminations
- (E) 30A Breaker Panel GEZ4A-32-34-36
- Complete Startup and Testing
- Electrical Safe-Off – LOTO
- Remove 2nd (N) Kaeser SK 15 from Temporary Location. Rig, Set, Seismically Anchor in Final Location.
- Install (1) (N) Kaeser SK 15 Rotary Screw Compressor
- Phase 1 - Designated Temporary Air Compressor
Description
Kaeser Control Air Compressor System Maintenance Upgrade
Scope of Work
- Provide and Install (2) (N) Kaeser “Air Center” SK 15 Rotary Screw Compressors
- 71 CFM @ 100 PSIG Each to Match Existing, 460V, 3 Phase, 60 Hz, 67 dB(A)
- 5 Gallon Air Receiver with Auto Receiver Tank Drain
- Built-In Refrigerated Kaeser Secotec Dryer
- Condensate Drain CAT Kit Air Center SK15
- Compressed Air Filters F22KE
- Condensate Treatment KCF-50 Condensate Treatment System
- Sigma Control 2 – Compressor “LEAD – LAG” Alternation
- Kaeser Factory Startup-Commissioning x 3
- Phase Planning
- Phase 1 - Designated Temporary Air Compressor
- Rig, Set, and Anchor (1) (N) Kaeser SK 15 Rotary Screw Compressor
- Plumbing
- Provide Temporary POC – Complete POC with Flexible Compressed Air Hose Connection
- Electrical
- Safe-Off - LOTO, Disconnect Power Feeding (1) of the Existing Kaeser Compressors
- (E) 30A Breaker Panel GEZ4A-32,34,36
- Complete Power Wiring to Temporary Compressor Location – Terminate Wires
- Startup and Test
- Safe-Off - LOTO, Disconnect Power Feeding (1) of the Existing Kaeser Compressors
- Phase 2 - Demo
- Demo and Removal of Existing Kaeser SK 19 Rotary Screw Compressors
- Electrical Demo – Including Safe-Off – LOTO
- (E) 30A Breaker Panel GEN4-7,9,11
- Cleanup (E) Equipment Pad
- Phase 3 – (N) Control Air Compressor CAC-2
- Install (1) (N) Kaeser SK 15 Rotary Screw Compressor
- Rig, Set, Seismically Anchor
- Complete Plumbing POC + Condensate Drains
- Complete Electrical Power Conduit – Wire – Terminations
- (E) 30A Breaker Panel GEN4-7,9,11
- Startup and Test
- Phase 4 – (N) Control Air Compressor CAC-1
- Remove 2nd (N) Kaeser SK 15 from Temporary Location. Rig, Set, Seismically Anchor in Final Location.
- Electrical Safe-Off – LOTO
- (E) 30A Breaker Panel GEZ4A-32,34,36
- Complete Plumbing POC + Condensate Drains
- Complete Electrical Power Conduit – Wire- Terminations
- (E) 30A Breaker Panel GEZ4A-32-34-36
- Complete Startup and Testing
- Electrical Safe-Off – LOTO
- Remove 2nd (N) Kaeser SK 15 from Temporary Location. Rig, Set, Seismically Anchor in Final Location.
- Install (1) (N) Kaeser SK 15 Rotary Screw Compressor
- Phase 1 - Designated Temporary Air Compressor