St. Joseph Health Cancer Center Round Barn Linear Accelerator Replacement

Industry: Hospitals and Healthcare
Type: Construction

Description

AES Group, Inc. acted as General Contractor for replacement of the Linear Accelerator Equipment.

Scope of Work

  • Pre-Air Balance per AIR BALANCE SCHEDULE
  • ICRA Containment
    • Per Approved ICRA Plan – Scope TBD
  • Demo per
    • Demo and Removal of (E) LINAC Equipment – Varian
    • Concrete – Removal of (E) Base Frame as Required
    • Concrete Saw Cut – Floor Trench from Modulator to (N) LINAC
    • Demo and Removal of (E) Compressed Air System - TBD
  • Electrical – Blakeslee Electric
    • Noted: (E) Conditions that were Visible During 4-28-22 Site Visit
    • Underground – Above Ceiling Electrical as Required
  • Concrete Infill –
  • Electrical Wiring and Terminations as Required for Varian Equipment Startup
    • Main Circuit Breaker Scope of Work – Blakeslee Electric Proposal PENDING
    • ICRA Containment
    • Demo
  • (N) Wall Framing – Backing as Required
  • (N) Dry Wall – Lead Lined – Finish as Required
  • (N) Acoustical Ceiling Grid – Ceiling Tiles
  • (N) Flooring
  • Rigging – Set – Seismically Anchor (N) LINAC Equipment
  • (N) Casework
  • Mechanical – HVAC – Plumbing
    • Chilled Water System Plumbing Connections – per TrueBeam Coolant System Diagram
    • (N) Chiller
    • (N) AHU
    • (N) HVAC ceiling Duct Work
  • A2 TrueBeam Sagittal Wall Elevation Equipment – Mounting
    • CCTV Camera
    • In Room Monitor – Varian Supplied Mounting Bracket
    • Optical Imaging Equipment – Varian Supplied Mounting Bracket
    • Live View Camera with Mic
    • Microphone Ceiling Mount
  • Fire Sprinklers –  Relocation
  • Paint
  • Cleanup
  • Equipment Testing as Required
  • Demo and Removal of Temporary Infectious Control Containment
  • Final Cleanup
  • Post Air Balance

 

  • IOR – OSHPD Inspection as Required

 

Description

AES Group, Inc. acted as General Contractor for replacement of the Linear Accelerator Equipment.

Scope of Work

  • Pre-Air Balance per AIR BALANCE SCHEDULE
  • ICRA Containment
    • Per Approved ICRA Plan – Scope TBD
  • Demo per
    • Demo and Removal of (E) LINAC Equipment – Varian
    • Concrete – Removal of (E) Base Frame as Required
    • Concrete Saw Cut – Floor Trench from Modulator to (N) LINAC
    • Demo and Removal of (E) Compressed Air System - TBD
  • Electrical – Blakeslee Electric
    • Noted: (E) Conditions that were Visible During 4-28-22 Site Visit
    • Underground – Above Ceiling Electrical as Required
  • Concrete Infill –
  • Electrical Wiring and Terminations as Required for Varian Equipment Startup
    • Main Circuit Breaker Scope of Work – Blakeslee Electric Proposal PENDING
    • ICRA Containment
    • Demo
  • (N) Wall Framing – Backing as Required
  • (N) Dry Wall – Lead Lined – Finish as Required
  • (N) Acoustical Ceiling Grid – Ceiling Tiles
  • (N) Flooring
  • Rigging – Set – Seismically Anchor (N) LINAC Equipment
  • (N) Casework
  • Mechanical – HVAC – Plumbing
    • Chilled Water System Plumbing Connections – per TrueBeam Coolant System Diagram
    • (N) Chiller
    • (N) AHU
    • (N) HVAC ceiling Duct Work
  • A2 TrueBeam Sagittal Wall Elevation Equipment – Mounting
    • CCTV Camera
    • In Room Monitor – Varian Supplied Mounting Bracket
    • Optical Imaging Equipment – Varian Supplied Mounting Bracket
    • Live View Camera with Mic
    • Microphone Ceiling Mount
  • Fire Sprinklers –  Relocation
  • Paint
  • Cleanup
  • Equipment Testing as Required
  • Demo and Removal of Temporary Infectious Control Containment
  • Final Cleanup
  • Post Air Balance

 

  • IOR – OSHPD Inspection as Required